Bladt Industries is to fabricate 72 transition pieces for Vattenfall's over 600MW Krieges Flak offshore wind farm off the Danish coast.
Production is set to start in July next year and take about 12 months to complete and deliver.
The work will be carried out at Bladt's Aalborg facility in Denmark.
The transition pieces will have a diameter of up to 6.4 metres, a length of 16 metres and a weight of 160 tonnes, the company said.
Bladt head of commercial and sales, wind and energy Lars Bender said: “We value our cooperation with Vattenfall highly, and we are very pleased to be working with Vattenfall on the Kriegers Flak project."
We look forward to being part of making this project a success for all parties.
Source:renews