Borssele 1&2 TPs take shape on Teesside

Published:

Teesside fabricator EEW Offshore Structures Britain has rolled out the first steel structures for the transition pieces for Orsted’s 752MW Borssele 1&2 offshore wind farm, which will be located off the Dutch coast.

The company said the structure, the first of the 35 TPs EEW OSB will make, was on its way to the blast shed.

Danish outfit Bladt Industries will supply the other 59 transition pieces for the project.

Sif and EEW SPC will each deliver half of the 94 monopile foundations.

Borssele 1&2 will feature 94 Siemens Gamesa 8MW turbines and is scheduled to come online in 2020.