Tema Port expansion works finalised two months ahead of schedule

On 30th April 2020, Meridian Port Services Limited successfully completed the entire Phase 1 works of the Tema Port Expansion Project (also known as Terminal 3 of Tema Port).

Tema Port expansion works finalised two months ahead of schedule
Photo: Tema Port

As per the terms of the Concession, MPS Terminal 3 was expected to Go-Live on 28th June 2019 on 2 berths and the entire Phase 1 works were due to be completed on 28th June 2020.

Both due dates were successfully achieved and works were completed ahead of schedule. The combination of a great team work, solid project finance and determined shareholders were among the main contributors to the success in delivering this mega infrastructure ahead of the contractual date in 3.5 years (41 months).

The new harbour basin was created on a 3 Km long beach directly on the Atlantic Ocean and right on the Meridian Timeline. Building into the sea, from the beach, the breakwater root goes 1,550m into the ocean with a 2 Km long arm extending eastwards from the root of the breakwater parallel to the quay wall. The 3,558 m long breakwater is harbouring a vast 450 Hectares (1,110 Acres) of maritime waterfront.

The new harbour basin is accessible through a 3,500 m long by 225 m wide Entrance Channel into a turning basin/circle of 500m diameter. The Access Channel has been dredged to -18.7m, Turning Basin to -17.4m and -16.9m by the quay wall to accommodate 16m draft vessels to dock alongside all berths.

The Phase 1 scope of works included building a 1,000 m long wharf which consists of 3 berths and 98 Hectares (242 Acres) terminal facility on land reclaimed from the sea with all drainage, sewage, water, fire, electrical and IT services, 45 million paving blocks laid down, a 12 MW back-up power station, major facilities including administration buildings for MPS and the Authorities, a maintenance workshop, a 60 bay unstuffing shed for Customs, 6 scanners, several gate facilities, a fire plant,  sewage treatment facilities and 1400 reefer container plugs.