Global Offshore completes cable installation campaign at Danish Kriegers Flak OWF

Global Offshore and part of the Global Marine Group, has completed their cable installation campaign at Vattenfall’s Danish Kriegers Flak Offshore Wind Farm.

Global Offshore completes cable installation campaign at Danish Kriegers Flak OWF
Photo: Global Offshore

The initial phase of work, completed last year, saw Global Offshore utilise their multi-purpose PLP240 pre-lay plough, mobilised on the Havila Jupiter, to carry out route clearance totalling approximately 158km.

The second phase, which commenced in September 2020, included the installation of 72 inter-array cables, utilising Normand Clipper, and the jet trenching of 72 routes using the Q1400 aboard sister vessel, Normand Cutter. Following the cable installations, the PLP240 returned to site to conduct backfilling operations, the first operation of its kind on an inter-array grid.

Prior to the commencement of the second phase, Global Offshore upgraded the Normand Clipper for power cable work. With the addition of a 4,000 tonne cable carousel, two 15-tonne cable tensioners, a 25-tonne quadrant deployment frame and a fully integrated control system, the 127.5m cable-laying vessel enables Global Offshore to continue providing a flexible, efficient and reliable service for their clients despite the COVID-19 pandemic, with the extensive operational challenges this has created.

Mike Daniel, Managing Director of Global Offshore, said:

“We are delighted to report the successful installation of all 72 inter-array cables at Danish Kriegers Flak Offshore Wind Farm. Despite COVID-19 restrictions and the associated challenges, extreme weather, and complex seabed conditions, our expert teams have met client expectations and completed this project safely, in under six months.”

Ian Bremner, Project Director at Vattenfall, said:

“Global Marine Group has shown professionalism in their operations and solution-oriented thinking, delivering a high standard of engineering to deal with the technical challenges during work execution. Our partner has worked safely throughout the COVID-19 pandemic alongside other ongoing site operations, contractors and the Vattenfall project team.”

Global Offshore continues to see increased demand for their services, which is testament to their operational delivery teams and extensive track record of successful offshore renewables project completions.