ClassNK issues AiP for conversion plan of medium-sized SEP vessel

This project involves a semi-sub floater developed by JMU, and a large WTG to be installed by converted SEP vessel.

ClassNK issues AiP for conversion plan of medium-sized SEP vessel

ClassNK has issued an Approval in Principle (AiP) for the conversion plan of the medium-sized self-elevating platform (SEP) vessel for the installation of large wind turbine generator (WTG) on a semi-sub floater in port jointly developed by TOA Corporation (TOA), NIHON SHIPYARD CO.,LTD. (NSY), and Japan Marine United Corporation (JMU).

This project involves a semi-sub floater developed by JMU, and a large WTG to be installed by converted SEP vessel. As a solution to the current lack of port facilities for installing a large wind turbine on a foundation at ports in Japan, TOA, NSY and JMU have been jointly researching and developing a method to convert a medium-sized SEP vessel to be used as a jacked-up tall crane in a port. 

Such three-party's joint R&D is based on the SEP vessel (equipped with a 1,250-ton crane) under the construction at JMU shipyard and to be co-owned by two companies including TOA corporation after her delivery. The converted SEP will enable the installation of large wind turbines even at ports without adequate facilities and is expected to promote the expansion of floating offshore wind power generation by providing a wider range of base port options.

ClassNK carried out a review of the jointly developed conversion plan in line with Part O of the Rules for the Survey and Construction of Steel Ships and issued the AiP on verifying conformity to the prescribed requirements.