Nord Stream 2 AG, a subsidiary of Russia’s Gazprom and operator of the Nord Stream 2 offshore gas pipeline, has submitted a third application for a route through Danish waters while accusing Denmark of making deliberate attempts to delay the project.
This third application for the pipeline route through Danish waters was submitted on Monday, April 15 more than two years after submitting the first application.
The pipeline operator said on Monday that the third application, together with the Environmental Impact Assessment (EIA), covers a route in the Danish exclusive economic zone (EEZ) in the waters south of Bornholm. This application and the EIA has been submitted in accordance with the decision made by the Danish Energy Agency (DEA) on March 26, 2019.
According to the operator, the EEZ border between Poland and Denmark was previously disputed and therefore the area was not available for any project developer. An agreement has been reached between the two countries, which, however, has not yet been ratified by Poland, the pipeline operator explained.
Nord Stream 2 already has two pending applications with the DEA.
Namely, in January 2018, the amended Danish Continental Shelf Act entered into force with retroactive effect only for the Nord Stream 2 project. The law gives the Danish Minister of Foreign Affairs the right to veto infrastructure projects running through territorial waters on political grounds. Such a judgement from the Ministry of Foreign Affairs has now been pending for 16 months. Nord Stream 2 AG has not received any response at all.
In August 2018, after 8 months without any indication of the timing of the Minister of Foreign Affairs recommendation, Nord Stream 2 was therefore forced to apply for a second, alternative route outside Danish territorial waters, north-west of Bornholm through the Danish EEZ.
Nord Stream 2 AG claims that both permitting processes, which included consultations with the public and expert authorities, nationally and internationally (the so-called Espoo procedure), have shown that all technical and environmental prerequisites are fulfilled and a construction permit could be granted for either route.