4.7 C
New York
Home Blog Page 1113

Ineffective enforcement of safety standards leads to injury

0

As IMCA informs an engineer was injured as he was walking in the engine room searching for a tool and he stepped on a loose floor plate. The floor plate was not bolted down and slipped sideways. The engineer suffered a large laceration to his abdomen, which made him go to the local hospital.

An engineer was injured during a dry dock. Namely, as he was walking in the engine room searching for a tool he stepped on a loose floor plate. The floor plate was not bolted down and slipped sideways.

As the plate moved, his leg started falling to the bilge well below, and the opposite end of the plate flipped upwards and struck his abdomen. He sustained a large laceration to his abdomen which was attended to in the local hospital and needed seven days off work to recover.

Probable cause

According to IMCA, the factors that contributed to the incident are the following:

  • No stopping mechanisms were fitted on the supporting frames/bars of the plates in order to stop these plates from sliding to the side. One particular plate was bent upwards at one corner and was able to slide freely if not bolted down;
  • An existing unsafe condition (the loose floor plate) had been spotted but had not been reported or addressed;
  • The permit to work (PTW) closure protocol following the earlier generator maintenance was not followed. No check had been made that the worksite had been returned to safe condition;

Moreover, root cause analysis identified that standards, policies and administrative controls were not used effectively and enforcement was not adequate. Specifically:

  • The shipyard safety bridging document had been signed, but was not properly completed and did not effectively bridge between vessel and shipyard safety systems;
  • There had been daily morning meetings of supervisors of all parties in attendance, but these meetings had discontinued a week prior to the incident.

In addition, on a day-to-day level, there were gaps in enforcement of the following procedures:

  • Job safety analysis (JSA) and task planning;
  • Personal protective equipment (PPE) – the injured person was wearing a light t-shirt instead of a full coverall which contributed to the severity of the injury;
  • Hazard observation – the hazard posed by the existing arrangements of the flooring plates in the engine room had not been properly identified;
  • Managing contractors and third-parties – successful integration and supervision of sub-contractor workforce was not applied despite procedures being in place. This led to a loss of control and safety oversight of their activities to some extent as well as a diminishing of the safety culture.

Lessons learned

After the incident, the IMCA concluded to the following lessons were learned:

  • Attention to detail; personal safety is an individual as well as collective responsibility. In this case, both the unsecured deck plates and IP’s insufficient PPE were noticed but neither concern was raised further or addressed;
  • Failure to properly coordinate activities and to supervise the jobs performed by sub-contractors for safe work can lead to serious consequences;
  • The shipyard safety bridging document sets the standard for the importance of safety within a shipyard period. The document dictates the involvement of the Technical Superintendent conducting supervision as well as vessel personnel and all contractors involved.

In order to prevent a similar incident from happening in the future:

  • Stoppers were fitted for plates to prevent recurrence;
  • Loose floor plates were secured by bolts;
  • A hazard hunt inspection was carried out to identify all similar loose floor plates;
  • The safety inspection schedule and risk assessment were modified to include checking of floor plates, gratings etc.;
  • Re-assess high level response to shipyard safety was re-assessed.

Source:safety4sea

Bibby lights fuse on Dutch bomb hunt

0

UK marine outfit Bibby Hydromap has started an unexploded ordnance survey for Vattenfall at the site of the 700MW Hollandse Kust Zuid 1&2 offshore wind farm off the coast of the Netherlands.

Vessels Bibby Tethra (pictured) and Bibby Athena will together acquire over 4,000-line km of high-density magnetometer, side scan sonar, multibeam echosounder and parametric sub-bottom data at the site 22km from shore, the surveyor said.

The company said each vessel is equipped with sensors, including dual EIVA ScanFish ROTVs with four magnetometers.

Bibby Hydromap added that it secured the contract earlier this year following a competitive bid process.

Bibby HydroMap project manager Daniel Jenkins said: “We are delighted to be working with Vattenfall on Hollandse Kust Zuid in 2019 to support their renewable goals."

Utilising the latest offerings from industry leading suppliers we are able to provide a highly effective and efficient UXO survey methodology, applicable to even the most environmentally challenging of sites.

Hollandse Kust Zuid 1&2 is scheduled for completion in 2022.

Source:renews

Tanker crew electrocuted, medevaced, South China sea

0

Product tanker PENYUAN reqested medical assistance to electrocuted Filipino crew in the afternoon Mar 9, while en route from Ho Chi Minh Vietnam to Guangzhou China.

The ship was some 50 nm off Nha Trang Province coast. Vietnamese MRCC advised first-aid measures, later it was decided, that seaman is in need of hospitalization.

Tanker turned to Vietnam coast to meet SAR ship, seaman was medevaced at around 1000 LT Mar 10. 30-year old Filipino seaman was electrocuted during work, no other details given. The ship understood to resume voyage. 

Source:fleetmon

BP Awards Contracts to McDermott and BHGE for Greater Tortue Ahmeyim Natural Gas Project

0

McDermott International, Inc. and Baker Hughes, a GE company have announced today that they have been awarded subsea umbilicals, risers and flowlines and subsea production system equipment contracts by BP for the Greater Tortue Ahmeyim natural gas project, located offshore Mauritania and Senegal. BP, BHGE and McDermott are working together to realize efficiencies, synergies and enhanced delivery times.

McDermott was awarded a substantial* engineering, procurement, construction and installation (EPCI) SURF contract. McDermott plans to use its upgraded Amazon vessel, DLV 2000, North Ocean 102 (NO 102) and third-party vessels to support installation scheduled to begin in late 2020. The Amazon modifications are scheduled to be completed before the installation campaign begins and will include a multi-joint (hex) J-Lay system to handle the most challenging ultra-deepwater projects as well as the addition of a multi-joint facility, dual pipe loading cranes and additional power generation. McDermott-designed pipeline and riser structures will be fabricated at its yard in Batam, Indonesia.

BHGE is demonstrating the benefits of early-engagement and collaboration – some of the key components of Subsea Connect – as well as bringing its expertise in deepwater, long-offset gas projects. The company will provide five large-bore deepwater horizonal xmas trees (DHXTs), a 6-slot dual bore manifold, a pipeline end manifold, subsea distribution units (SDUs), three subsea isolation valves (SSIVs), diverless connections and subsea production control systems, specifically designed to enable the future integration of additional wells for the first phase of the development.

"This contract marks a number of firsts: our first significant subsea EPCI project in West Africa; the first project using our state of the art pipelay vessel Amazon; and our support of BP's first entry into Senegal and Mauritania. This project is also of significant importance in support of our aspirations in this region," said Tareq Kawash, McDermott's Senior Vice President for Europe, Africa, Russia and Caspian. "Our collaboration with BHGE allows us to offer BP an integrated approach that builds on our proven solutions. We look forward, along with BHGE, to deliver this landmark project to BP with the highest levels of safety and quality."

"Together with McDermott, we will deliver the best-in-class solution to BP with cost-efficiency and industry-leading safety. These awards demonstrate the value of early-engagement, collaborative partnerships and holistic project planning, which are very much central to our new approach to subsea developments, Subsea Connect," said Graham Gillies, BHGE's Vice President, Subsea Production Systems & Services. "This major deepwater gas development is strategically important for Mauritania and Senegal's domestic and global gas supply, and supports the industry's drive for a more sustainable, lower carbon future."

Australia Navy Nabs Two Tonnes of Hashish

0

Royal Australian Navy reports that its frigate HMAS Ballarat seized two tonnes of hashish worth approximately $71 million in street value during a boarding operation on 28 February 2019.

The boarding was conducted in international waters by the Combined Task Force 150 under the direction of the Combined Maritime Forces as part of Operation Manitou.

Following the suspicious behavior of a local fishing vessel (dhow), the boarding team searched and discovered 100 hessian bags of hashish on board, which were transferred to Ballarat for testing and then destroyed.

Boarding Officer Lieutenant Lachlan Turner praised his team for conducting a safe and successful boarding.

“Our training, equipment and commitment to the job at hand makes for a very effective boarding team,” Lieutenant Turner said. “We continue to ensure the same high standard on each and every occurrence."

This is the sixth seizure of narcotics by Ballarat during her current deployment to the Middle East, departing Fleet Base West in Rockingham in October last year.

The previous boardings have resulted in Ballarat seizing and destroying about 1.2 tonnes of heroin and 5.2 tonnes of hashish.

Operation Manitou is the Australian Government's contribution to support international efforts to promote maritime security, stability and prosperity in the Middle East.  An enhanced security environment ensures Australia's safe and open access to the region while fostering trade and commerce.

Source:marinelink

Delmar Completes West Phoenix Disconnect

0

The provider of offshore mooring and subsea services, Delmar Systems said it completed an eight-line disconnect of the mooring system on Seadrill’s West Phoenix semi-submersible drilling rig on the UK Continental Shelf, using its RAR Plus Technology.

The rig disconnection was performed in two and a half hours without needing anchor handling tug supply (AHTS) vessel assistance. The West Phoenix is currently under contract with Equinor for a three well campaign, all of which are using Delmar’s Releasable Anchor Mooring System.

Delmar’s RAR Plus is the first ever dual-release action (acoustic and mechanical) rig anchor release. It allows for immediate rig transit after release with the RAR Plus’ nested in their trigger sleeves against the rig fairlead. This eliminates the weather window requirement that is typical for AHTS operations during a traditional rig disconnect.

Jan Petter Leirvåg, Equinor’s Senior Consultant- Rig Move Operations said, “We had the privilege of being the first to perform a successful disconnect in the North Sea without support of AHTS vessels. We are always looking for improvements when it comes to safe and efficient operations on our rig moves and the RAR Plus is definitely an improvement. The West Phoenix will have the Delmar RAR Plus’ on three wells to begin, and after a successful test period we will look for opportunities across our rig fleet. Good corporation with Moray Systems and Delmar, has made this a true success.”

John Shelton, Delmar System’s Vice President of Technical Services said, “We are excited to introduce our Releasable Anchor Mooring System to the North Sea and save our customers significant rig time and vessel time during rig disconnections using RAR Plus technology. We look forward to the continued success of this campaign with Equinor and many future ventures in the North Sea.”

The first disconnect of the three well program was performed using group line releases of two lines, two lines, and four lines. Equinor’s three well campaign is scheduled to continue through Q3 2019.

Source:marinelink

Port of Virginia Accelerates Massive Expansion

0

The Port of Virginia has completed the first stage of its US$375 million expansion after the Norfolk International Terminals’ (NIT) 12 new container stacks 24 rail-mounted gantry (RMG) cranes were put into action.

According to a statement, the project, which is meant to turn Virginia into the main container shipping port on the US east coast, commenced in January 2018 and is due to be completed by June 2020.  

The port’s overall expansion will cost $700 million, the centerpiece of which will be the construction of 30 semi-automated container stacks at the South NIT, which will be served by 60 new RMGs.

Once finished, it will increase the NIT’s annual throughput capacity by approximately 46% to 1.25 million TEUs.

John F. Reinhart, CEO and executive director of the Virginia Ports Authority, said: “A little more than a year ago an area the size of 30 football fields was cleared and today we’re processing thousands of containers through that same space."

We are forty-percent of the way through construction and are seeing good flow at the gates and are maintaining a strong, customer-focused effort during construction.

PTI reported in February 2019 that Virginia’s expansion was well under way when the Virginia International Gateway (VIG), another terminal at the port completed the first of three container stack-yard installations.

“This milestone comes on the heels of our announcement in February that we have completed the stack-yard work at Virginia International Gateway,” Reinhart continued.

That project brought 13 new container stacks into service and gives us the capability to process 1.2 million lifts a year at VIG.

“The $700 million investment being made in The Port of Virginia puts it in the best position to become the US East Coast’s premier port and a major hub for ultra-large container vessels.” 

Source:porttechnology

ESL Shipping reflags Haaga to Finnish flag

0

ESL Shipping says it has decided to reflag newbuilding Haaga to the Finnish flag from Portuguese flag as a part of the agreement with unions. Flag change took place today in Kokkola, Finland.

”We found a constructive solution with unions and are proud to finally hoist the Finnish flag onboard the Haaga”, says Mikki Koskinen, Managing Director of ESL Shipping.

Having all owned vessels under Finnish flag gives us synergies in crew replacement and rotation as well as improves the competitiveness of the whole fleet through introduction of the fleet wide mixed crewing model.

ESL Shipping Ltd is the leading carrier of dry bulk cargoes in the Baltic region. Our main clients are the power generation, steel and chemical industries to whom we carry raw materials such as coal, iron ore and limestone. ESL Shipping Ltd has been in business close to 70 years and is a subsidiary of Aspo Plc

Source:portnews

BW Offshore seals Maromba acquisition with Petrobras

0

BW Offshore has sealed a deal with Petrobras to acquire a 70% stake in the Maromba field, offshore Brazil, for $90m.

The Oslo-headquartered company, part of Singapore’s BW Group, had announced last week its intentions to acquire the field, both the 70% stake owned by Petrobras along with a 30% stake from Chevron. The acquisition of the Chevron stake is still pending board approval by Chevron.

Maromba is located in the Campos Basin and has potential recoverable resources of 100-150 million barrels of low-sulphur 16 API oil.

BW Offshore currently owns 15 FPSOs and says it intends to deploy one them to the field.

Carl Arnet, CEO of BW Offshore, commented: “Maromba meets many of the criteria our E&P strategy is founded on; proven resources, high upside potential, located in a country where we currently operate, phased development and the use of one of our own FPSOs."

We will pay approximately USD 1 per barrel of recoverable resources in an area we know well, and we are currently evaluating several development options within our phased development strategy that range from USD 3 to 7 of capital cost per recoverable barrel plus FPSO lease. Maromba has the potential to create significant value for the shareholders of BW Offshore.

 

ABS partners with SecurityGate to deliver the most in-depth cyber risk analysis in maritime

0

ABS Advanced Solutions (ABS) announced its partnership with SecurityGate, affording the most in-depth cyber risk analysis solution in the maritime market.

The effort integrates the ABS proprietary FCI Cyber Risk™ Methodology into the award-winning SecurityGate SaaS platform, further solidifying the ABS maritime cyber security leadership. The resulting dashboard provides an instant shared view, illustrating the degree of cyber risk across assets, operations and critical suppliers. 

Additionally, the SecurityGate software helps pinpoint unique remediation efforts to effectively showcase the return on investment of cyber risk mitigation strategies over time.

The ABS FCI Cyber Risk™ Methodology was developed following a two-year research contract with the Maritime Security Center—a U.S. Department of Homeland Security Center of Excellence—led by Stevens Institute of Technology and including the US Department of Defense.